Photos from week 7, February 26-March 3

Framing of the upstairs walls (our work) in preparation for wiring (also ours) and insulation (contractor.)  The sloping portions of the wall have been built down to have about 16″ of blown in high-density cellulose, and the attic will get about 2+ feet.  The knee wall space will be filled with insulation.

img_20170227_160528

img_20170227_160538

img_20170227_160549

img_20170228_154144

The garage windows were installed this week.

img_20170228_154105

Space above the garage for storage.

img_20170228_154459

img_20170228_154509

The “Polar Cave” is mostly gone with just some ice remaining in the ell crawl space.

img_20170302_152419

img_20170302_152433

Very little happened during the last days of the week due to (once again!) very cold temperatures although I was able to do the “attic” wiring and upstairs ceiling wiring one afternoon when the sun was on the roof and providing some heat.