Photos from week 15, May 1-7

Photos from week 15, May 1-7 are located below.

Drywall is ongoing and due to be finished by next Tuesday.

IMG_20170502_161442

The countertops were delivered and installed on Friday.

IMG_20170505_130914

IMG_20170505_131736

IMG_20170505_131742

 

IMG_20170505_132207

The large piece for the island.  The crew indicated that they sometimes handle pieces as much as three times the size of this piece.

IMG_20170505_132233

IMG_20170505_132242

IMG_20170505_132245

Drilling holes for the faucet.

IMG_20170505_134941

The completed installation.  The appliances are to be delivered next Wednesday.

IMG_20170505_164200

IMG_20170505_164213

IMG_20170505_164229

The shower door installed.

IMG_20170506_135540

The downstairs bathroom is nearly complete except for light fixtures.

IMG_20170506_135711