Photos from week 12, April 6-15

Some plumbing has been hooked up, and the well pump has been started to flush out the well and disinfect it.  Once the insulation is completed water will be allowed in the house pipes to check for any problems before the remaining drywall is completed.

IMG_20170407_144301

The Roxul insulation has been added to the internal walls upstairs in preparation for drywall work.

IMG_20170408_104342

IMG_20170408_104356

IMG_20170408_151223

IMG_20170408_151307

The skylight openings were cut out and the skylights installed early this week.  They dramatically increase the amount of light in the upstairs rooms and staircase.

IMG_20170410_084103

IMG_20170410_092730

The third skylight was delayed until the first two were completely finished.

IMG_20170410_112255

IMG_20170410_164118

Some kitchen cabinet doors have been added while others are waiting for their knobs.

IMG_20170410_163827

The house in Thorndike is on the market with several showing in the first week.

IMG_20170413_074312

The internet lines were originally routed to the main electrical panel, but in retrospect, it made more sense to re-route them to an area in the basement near the stairwell where they can be tied together with a wireless router which in this central location should serve most of the house along with a fast switch to tie the other wired lines together.

IMG_20170413_135648

A “ships ladder” like stair has been added to the garage.  While it is narrow, it provides easy access to the garage attic space. It will shortly get a ships ladder style railing, and the window needs to have a plexiglass cover added since it is not tempered glass.

IMG_20170413_140210

The remaining garage doors are in place, and the garage wiring is fully completed.

IMG_20170413_150604

IMG_20170414_141610

The presence of the stairs makes moving additional stuff over the garage much more feasible.

IMG_20170414_141633

The kitchen ell is now wired has been insulated except for the ceiling which will remain uninsulated until the masonry work is completed.

IMG_20170414_141723

IMG_20170414_141731

One of our “crew” worked with his son for about 8 hours on Saturday to complete the rest of the cellulose insulation work.

IMG_20170415_131625

The hall bookcase and pantry cabinets and shelves have been painted although the face frames are still low priority as they do not affect the usefulness of the bookcase or pantry.

IMG_20170415_131613

IMG_20170414_143434

IMG_20170414_143429

The list of items to be completed by the contractor is rapidly shrinking and they hope to have all but some minor followup work completed by the end of next week although the drywall contractor for the upstairs and finishing between the modules will need at least an additional week.

While the drywall contractor is working inside, I hope to get the garage door trimmed in preparation for the garage door, and perhaps some additional preparation for siding (which is not a high priority yet.)  After that, hooking up the remaining plumbing, interior painting, floors, and staircase remain before requesting an occupancy permit so we could move in whenever we are ready.